INTERNATIONAL JOINT VENTURE BETWEEN ASEAN AND GULF: BIDDING AND DELIVERING BAHRAIN INTERNATIONAL FORMULA-1 CIRCUIT; pp. 357–382
PDF | doi: 10.3176/tr.2014.4.04

Authors
Hamzah Abdul-Rahman, Chen Wang, Lincoln C. Wood, Suraya Ismail
Abstract

A foreign contractor can resort to a partnering or joint-venture strategy with a host contracting firm to bid for a major international construction project. This paper presents a case study in the Bahrain FORMULA-1 Circuit (BFC) project focusing mainly on its tendering and construction stages, which is lacking in literatures. Findings illustrate that the success in such an international pact include: advanced technical and engineering expertise; selection of a committed partner; management expertise; creating and sustaining good working environment; appropriate risk management; maintaining a reliable interna­tional materials supply chain; and efficient project planning and tracking system. Manage­ment expertise is the most important factor because of the peculiarities and problems of international projects. This case study is able to assist practitioners to devise their own approach in overcoming the challenges and dynamic influences in the international construction market.

References

Abba, W. F. (1996) “Earned Value Management: reconciling government and commercial practices”. Program Manager 26, 58–67.

Abdul-Rahman, H. and F. Mohd-Rahim (2006) Challenges and opportunities of international construction. Kuala Lumpur: University of Malaya Press.

Abdul-Rahman, H. and M. A. Berawi (2002) “Managing change in construction contracting”. Contract Management 42, 10–16.

Adams, F. K. (2008) “Risk perception and Bayesian analysis of international construction contract risks: the case of payment delays in a developing economy”. International Journal of Project Management 26, 2, 138–148.
http://dx.doi.org/10.1016/j.ijproman.2007.05.007

Adams, Z. and R. Fuss (2010) “Macroeconomic determinants of international housing markets”. Journal of Housing Economics 19, 1, 38–50.
http://dx.doi.org/10.1016/j.jhe.2009.10.005

Aharoni, Y. (1966) The foreign investment decision process. Boston, MA: Harvard University Press.

Alnaser, W. E., S. D. Probert, S. El-Masri, S. E. Al-Khalifa, R. Flanagan, and N. W. Alnaser (2006) “Bahrain’s Formula-1 racing circuit: energy and environmental considerations”. Applied Energy 83, 352–370.
http://dx.doi.org/10.1016/j.apenergy.2005.04.006

Alnaser, N. W., R. Flanagan, S. E. Al-Khalifa, R. Mumtaz, S. El-Masri, W. E. Alnaser (2007) “Architectural, construction and environmental matters of Bahrain’s International Formula 1 Circuit”. Building and Environment 42, 1783–1794.
http://dx.doi.org/10.1016/j.buildenv.2006.01.014

Anbari, F. T. (2003) “Earned value project management method and extensions”. Project Manage­ment Journal 34, 4, 12–23.

Ansoff, I. H. (1965) Corporate strategy. New York: McGraw-Hill.

Bradon, J. and M. Daniel (1998) “Implementing earned value easily and effectively”. Project Management Journal 29, 2, 11–18.

Bryman, A. (2004) Social research methods. 2nd ed. New York: Oxford University Press.

Betts, M. and G. Ofori (1994) “Strategic planning for competitive advantage in construction: the Institutions”. Construction Management and Economics 12, 203–217.
http://dx.doi.org/10.1080/01446199400000029

Buckley, P. J. and M. C. Casson (1976) The future of the multinational enterprise. London: Macmillan.

Bon, R. and Crosthwaite, D. (2000) The future of international construction. London: Thomas Telford.

CSSC (1989) Investing in building 2001. University of Reading, Reading: Centre for Strategic Studies in Construction.

Chou, J. and J. Yang (2013) “Evolutionary optimization of model specification searches between project management knowledge and construction engineering performance”. Expert Systems with Applications 40, 11, 4414–4426.
http://dx.doi.org/10.1016/j.eswa.2013.01.049

Creswell, J. W. (1994) Research design: qualitative and quantitative approaches. California: Sage Publications.

Czarnigowska, A. (2008) “Earned Value as a tool for project control”. Budownictwo i Architektura 3, 2, 15–32.

Daniels, J. D. and L. H. Radebaugh (1998) International business: environments and operations. Burr Ridge, IL: McGraw-Hill.

Daniel, R. M. (1985) “Earned value technique for project performance”. Journal of Management in Engineering 1, 2, 79–94.
http://dx.doi.org/10.1061/(ASCE)9742-597X(1985)1:2(79)

Dikmen, I., M. T. Birgonul, and S. Han (2007) “Using fuzzy risk assessment to rate cost overrun risk in international construction projects”. International Journal of Project Management 25, 5, 494–505.
http://dx.doi.org/10.1016/j.ijproman.2006.12.002

Dikmen, I., M. T. Birgonul, and A. K. Gur (2007) “A case-based decision support tool for bid mark-up estimation of international construction projects”. Automation in Construction 17, 1, 30–44.
http://dx.doi.org/10.1016/j.autcon.2007.02.009

Drewer, S. (2001) “A perspective on the international construction system”. Habitat International 25, 1, 69–79.
http://dx.doi.org/10.1016/S0197-3975(00)00027-8

Dunning, J. H. (1977) “Trade, location of economic activity and the MNE: a search for an eclectic approach”. In The International Allocation of Economic Activity, 395–418. B. Ohlin, P. O. Hesselborn, and P. M. Wijkman, eds. London: Macmillan.

El-Sayegh, S. M. (2008) “Risk assessment and allocation in the UAE construction industry”. International Journal of Project Management 26, 4, 431-438.
http://dx.doi.org/10.1016/j.ijproman.2007.07.004

ENR (1991) “The top 250 international contractors: Instability slows growth abroad”. Engineering News-Record 22 July, 30–43.

ENR (1992) “The top 250 international contractors: firms set sail for hot markets”. Engineering News-Record 24 August, 34–45.

ENR (2000) “The top 225 international contractors: slow growth, high hopes”. Engineering News-Record 14 August, 48–87.

Flanagan, R. (1994) “The features of successful construction companies in the international construction market”. In Strategic planning in construction: proceedings of the A. J. Etkin international seminar on strategic planning in construction companies. (A. Warzawski, and R. Navon.) Haifa, Israel, 8–9 June, 304–318.

Fleming, Q. W. and J. M. Koppelman (2002) “Using earned value management”. Cost Engineering 44, 9, 32–36.

Halawa, W. S., A. M. K. Abdelalim, and I. A. Elrashed (2013) “Financial evaluation program for construction projects at the pre-investment phase in developing countries: a case study". International Journal of Project Management 31, 6, 912–923.
http://dx.doi.org/10.1016/j.ijproman.2012.11.001

Han, S. H., D. Y. Kim, H. S. Jang, and S. Choi (2010) “Strategies for contractors to sustain growth in the global construction market”. Habitat International 34, 1, 1–10.
http://dx.doi.org/10.1016/j.habitatint.2009.04.003

Hasegawa, F. (1988) Built by Japan: competitive strategies of Japanese construction industry. New York: Wiley.

Hammer, M. and J. Champy (1993) Reengineering the corporation: a manifesto for business revolution. London: Brierley.

Hillerbrandt, P. M. (2000) Economic theory and the construction theory. 3rd ed. Basingstoke: MacMillan.

Howes, R. (2000) “Improving the performance of earned value analysis as a construction project management tool”. Journal of Construction and Architecture Management 7, 4, 399–411.
http://dx.doi.org/10.1046/j.1365-232X.2000.00171.x

Hung, A. L. W., G. M. Naidu, S. T. Cavusgil, R. C. Yam (2002) “An exploratory study of project based international joint ventures: the case of Chek Lap Kok Airport in Hong Kong”. International Business Review 11, 505–522.
http://dx.doi.org/10.1016/S0969-5931(02)00034-3

Hymer, S. H. (1976) The international operations of national firms: a study of direct foreign investment. Doctoral thesis, MIT Press, Cambridge, MA.

International Construction Task Force (1993) Competing in the global market. Austin, TX: Construction Industry Institute.

Iranmanesh, S. H. and Z. T. Hojati (2008) “Designing a progress simulator for estimation of project completion cost and time”. In Proceedings of the international conference on project management (ICoPM), Petaling Jaya, Malaysia, November 18–20, 120–127.

Jia, G., X. Ni, Z. Chen, B. Hong, Y. Chen, F. Yang, and C. Lin (2013) “Measuring the maturity of risk management in large-scale construction projects”. Automation in Construction 34, 56–66.
http://dx.doi.org/10.1016/j.autcon.2012.10.015

Kerzner, H. (2001) Project management: a system approach to planning, scheduling, and control­ling. 7th ed. New York: John Wiley & Sons.

Kim, D. Y., S. H. Han, H. Kim, and H. Park (2009) Structuring the prediction model of project performance for international construction projects: a comparative analysis”. Expert Systems with Applications 36, 2, 1961–1971.
http://dx.doi.org/10.1016/j.eswa.2007.12.048

Kim, E. H., G. W. William, and R. D. Michael (2003) “A model for effective implementation of earned value management methodology”. International Journal of Project Management 21, 375–382.
http://dx.doi.org/10.1016/S0263-7863(02)00049-2

Kim, S. (1988) “The Korean construction industry as an exporter of services”. The World Bank Economic Review 2, 2, 225–238.
http://dx.doi.org/10.1093/wber/2.2.225

Kindleberger, C. P. (1969) American business abroad: six lectures on direct investment. New Haven: Yale University Press.

Lewis, J. P. (2001) Project planning, scheduling, and control: a hands-on guide to bringing projects in on time and on budget. 3rd ed. New York: McGraw-Hill.

Li, X. (2013) “TIMODAZ: a successful international cooperation project to investigate the thermal impact on the EDZ around a radioactive waste disposal in clay host rocks”. Journal of Rock Mechanics and Geotechnical Engineering 5, 3, 231–242.
http://dx.doi.org/10.1016/j.jrmge.2013.05.003

Linder, M. (1994) Projecting capitalism: a history of the internationalization of the construction industry. Westport: Conn.

Momaya, K. and K. Selby (1998) “International competitiveness of Canadian construction industry: a comparison with Japan and the United States”. Canadian Journal of Civil Engineering 25, 640–652.
http://dx.doi.org/10.1139/l98-004

Ofori, G. (2003) “Frameworks for analyzing international construction”. Construction Management and Economics 21, 379–391.
http://dx.doi.org/10.1080/0144619032000049746

Oz, O. (2001) “Sources of competitive advantage of Turkish construction companies in international markets”. Construction Management and Economics 19, 135–144.
http://dx.doi.org/10.1080/01446190010009988

Ozorhon, B., D. Arditi, I. Dikmen, and M. T. Birgonul (2007) “Effect of host country and project conditions in international construction joint ventures”. International Journal of Project Management 25, 8, 799–806.
http://dx.doi.org/10.1016/j.ijproman.2007.05.003

Porter, M. E. (1985) Competitive advantage: creating and sustaining superior performance. New York: The Free Press.

Pralahad, C. K. and G. Hamel (1990) “The core competence of the corporation”. Harvard Business Review 3, 79–91.

Quak, S. K. (1990) Marketing abroad: exporting strategies for singapore construction firms. Singapore: Institute of South-East Asian Studies.

Rashid, A. A. (1990) Global strategies of construction firms. PhD thesis, University of Reading, Reading.

Seymour, H. (1987) The multinational construction industry. London: Croom Helm.

Strassman, P. and J. Wells (1988) Introduction: Global Construction industry. London: Croom Helm.

United Nations Centre for Transnational Corporations (UNCTC) (1989) Transnational corporations in the construction and design engineering industry. New York: United Nations.

Ustinovichius, L., G. Shevchenko, A. Barvidas, I.V. Ashikhmin, and D. Kochin (2010) “Feasibility of verbal analysis application to solving the problems of investment in construction”. Automation in Construction 19, 3, 375–384.
http://dx.doi.org/10.1016/j.autcon.2009.12.004

West, R. C. (1992) “Improving international competitiveness”. Journal of Professional Issues in Engineering Education and Practice 118, 2, 107–112.
http://dx.doi.org/10.1061/(ASCE)1052-3928(1992)118:2(107)

World Bank (2000) World development record, 2000/01. Washington DC: World Bank.

Yates, J. K., S. Mukherjee and S. Nijos (1991) Anatomy of construction industry competition in the year 2000. (Source Document, 64.) Austin, TX: Construction Industry Institute.

Ye, K., L. Shen, J. Zuo (2013) “Utilizing the linkage between domestic demand and the ability to export to achieve sustainable growth of construction industry in developing countries”. Habitat International 38, 135–142.
http://dx.doi.org/10.1016/j.habitatint.2012.05.008

Yin, R. K. (1994) Case study research: design and methods. 2nd ed. (Applied Social Research Methods Series; 5.) California: Sage Publications.

Zhao, X., B. Hwang, and G.S. Yu (2013) “Identifying the critical risks in underground rail inter­national construction joint ventures: case study of Singapore”. International Journal of Project Management 31, 4, 554–566.
http://dx.doi.org/10.1016/j.ijproman.2012.10.014

Back to Issue